How to Compare General Contractors in Dubai

Give contractors the same drawings, quantities and specifications, then compare the returned offers line by line. Look beyond the total: check exclusions, allowances, payment stages, named responsibilities and handover documents. The comparison sheet below helps find differences before you appoint a contractor.

Published by 800 Master RenovationsUpdated

Issue the same documents to every bidder

A useful contractor comparison asks whether each bidder understands the same property, proposed changes and delivery boundary. Start with a common issue pack. Then compare how each response treats existing conditions, civil and MEP interfaces, specialist packages, approvals, client-supplied items, access and close-out.

The objective is not to produce an artificial score from marketing claims. It is to identify material differences in scope, responsibility and evidence before an appointment is made. Any credential or project claim that matters to the decision should be checked against a current, relevant source supplied for that purpose.

  • One project brief and revision issued to every bidder
  • One comparison table for inclusions, exclusions and allowances
  • Named responsibility for design, approvals, procurement, testing and handover
  • Written clarification of assumptions before commercial selection

A six-step contractor comparison process

Keep the comparison traceable from the first issue pack to the final clarified offer.

  1. 01

    Prepare one project brief

    Record the property, use, included areas, retained elements, desired changes, known restrictions and available drawings or surveys.

  2. 02

    Issue the same scope information

    Give each contractor the same revision of drawings, BOQ, specification, responsibility questions and expected response format.

  3. 03

    Separate technical questions from preferences

    Resolve structure, services, waterproofing, life-safety, access and approval dependencies before comparing optional finishes or brands.

  4. 04

    Normalise the quotations

    Place quantities, specifications, exclusions, provisional items, client-supplied products and third-party responsibilities side by side.

  5. 05

    Clarify delivery controls

    Ask how revisions, substitutions, site discoveries, inspections, concealment and outstanding items will be documented.

  6. 06

    Record the final basis

    Attach agreed clarifications and document revisions to the commercial offer so the selected scope is identifiable later.

Evidence to request for the actual project

The relevant evidence depends on the property and scope. Ask for current documents and named responsibilities; a generic statement is insufficient.

Scope understanding
Marked inclusions, exclusions, interfaces and open questions against the issued documents

A clear list of uncertainties is more useful than silent assumptions.

Technical coordination
Proposed route for drawings, samples, submittals, specialist input and inspection points

Check who prepares and who reviews each item; do not assume every role sits with one company.

Commercial basis
BOQ, quantities, units, product assumptions, provisional items and change documentation

The quoted total should be traceable to a written scope and revision.

Approvals responsibility
Matrix for property documents, technical submissions, fees, inspections and third-party decisions

No contractor can replace the competent body that determines applicability or acceptance.

Close-out approach
Completion checks, outstanding-item record and applicable product, testing and access information

Agree the expected file before work closes so it does not need to be reconstructed at handover.

Put every contractor response on the same comparison sheet

DecisionComparison fieldWhat a clear response should identify
Issue basisDrawing, BOQ and specification revisions usedThe exact documents and clarifications included in the offer
Scope boundaryIncluded, excluded and client-supplied packagesWhere each package starts, finishes and connects to other work
Unknown conditionsInaccessible or unverified itemsDocumented assumption, allowance or investigation route
Technical responsibilityDesign, coordination, installation, testing and review rolesThe appointed party and deliverable for every specialist interface
ChangesRevisions, substitutions and discovered conditionsWritten evidence, approval route and separation from the base scope
Close-outCompletion, outstanding items and handover informationWhat will be checked and which applicable records will be assembled

Questions to ask before contractor selection

Ask the same questions in writing and attach the answers to the comparison. If a response changes the scope or specification, issue the clarification to every remaining bidder so the commercial basis stays consistent.

  • Which drawing, BOQ and specification revisions form the offer?
  • Which surveys or existing conditions still need verification?
  • What is excluded, provisional, client-supplied or assigned to a specialist?
  • Who prepares and reviews structural, MEP or other technical information where required?
  • Who supplies property documents and coordinates any applicable submission?
  • How are product substitutions and client changes documented?
  • Which inspections occur before work is concealed?
  • What completion checks and handover records are included?